2013/01/02 (Wed): |
Follow up: 1) 2) |
1) Weather: pm - pm raining |
2) Daily issue / task: - - |
3) Goods ordered / received: - - |
4) Feedback / problem: - - |
5) Work progress: - - - - |
2013/03/04 (Mon): |
Follow up: 1) 2) |
1) Weather: pm - pm raining |
2) Daily issue / task: - - |
3) Goods ordered / received: - - |
4) Feedback / problem: - - |
5) Work progress: - - - - |
2013/03/02 (Sat): |
Follow up: 1) 2) |
1) Weather: pm - pm raining |
2) Daily issue / task: - - |
3) Goods ordered / received: - - |
4) Feedback / problem: - - |
5) Work progress: - - - - |
2013/03/01 (Fri): |
Follow up: 1) 2) |
1) Weather: pm - pm raining |
2) Daily issue / task: - Chiew said he will order excavator on next Wednesday (6/3) to dig for manhole. - Ah Seng said the rooftop water outlet should flow downwards instead of side way, so the water flows faster. - |
3) Goods ordered / received: - Cement arrived 3.30pm - 50pkt - |
4) Feedback / problem: - - |
5) Work progress: - - - - |
2013/02/28 (Thu): |
Follow up: 1) 2) |
1) Weather: pm - pm raining |
2) Daily issue / task: - - |
3) Goods ordered / received: - Sand arrived 10.15am - 10wheels - Cement arrived 3.30pm - 50pkt |
4) Feedback / problem: - - |
5) Work progress: - - - - |
2013/01/30 (Wed): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To install basic lighting inside bungalow. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: - Aaron, Tony & Mak came to meet Amin about final touch up works & payment. ** Instruction from Tony & Mak: a) Steel structure must paint with anti-rust undercoat first. b) Cut off plants against wall near swimming pool, to do plaster & paint the wall. c) Amin (has agreed) to instruct his workers start to do touch up in & out of the bungalow. d) Master bedroom balcony's floor need to level with inside. e) 2nd floor water pipe (that exposed) need to be concealed. |
3) Goods ordered / received: - NIL |
4) Feedback / problem: - Rooftop steel material delivery delayed again: Lorry order wrongly (too small). Sam said will deliver by tmr (31/1) - Ateh not coming to work, said tmr. |
5) Work progress: - - - - |
2013/01/29 (Tue): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To install basic lighting inside bungalow. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: - Inside plumbing works done, the supervisor tested for water running. OK. - Tony called, ask to inform Aaron start to plan for painting job. |
3) Goods ordered / received: - NIL |
4) Feedback / problem: - Hassan send plaster workers to do passport, thus today no plaster work. - Rooftop steel material cannot deliver by today, will arrange tmr. - Ateh not coming to work, said tmr. |
5) Work progress: - - - - |
2013/01/28 (Mon) **Holiday: |
Follow up: |
1) Weather: |
2) Daily issue / task: |
3) Goods ordered / received: |
4) Feedback / problem: |
5) Work progress: |
2013/01/26 (Sat): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To install basic lighting inside bungalow. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: - Tom came, asking to make changes to stair's balcony door frame. |
3) Goods ordered / received: - NIL - |
4) Feedback / problem: - NIL |
5) Work progress: - - - - |
2013/01/25 (Fri): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To install basic lighting inside bungalow. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. 4) To do water-proofing & plaster for the pond, after completing the rooftop. |
1) Weather: 2.30pm - 6pm raining (very heavy) |
2) Daily issue / task: - Main entrance concrete slab (widen) completed. |
3) Goods ordered / received: - NIL |
4) Feedback / problem: - Last night (24/1) heavy rain causing the outside wall very wet, couldn't do plaster. - Because of heavy rain last night, discover a few spot of slab leaking water, causing the plastered ceiling getting wet. Jason has informed Mak. No choice but to wait for water-proofing floor done. - Ateh promised to come do the front drain, but again doesn't showed up. Jason called he said come next Tuesday (29/1) |
5) Work progress: - - - - |
2013/01/24 (Thu) **Holiday: |
Follow up: |
1) Weather: |
2) Daily issue / task: |
3) Goods ordered / received: |
4) Feedback / problem: |
5) Work progress: |
2013/01/23 (Wed): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To install basic lighting inside bungalow. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: 5pm start raining |
2) Daily issue / task: - Hassan start to build concrete slab to widen the entrance. |
3) Goods ordered / received: - NIL |
4) Feedback / problem: - Jason gave RM100 for DBKL officer. |
5) Work progress: - - - - |
2013/01/22 (Tue): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. 4) To install basic lighting inside bungalow. |
1) Weather: No rain |
2) Daily issue / task: - Swimming pool mosaic & wiring done. - Mak's staff brought one hacking machine to site, Jason let Hanif do necessary hacking job. |
3) Goods ordered / received: - Cement arrived 11am - 50pkt - Kapur arrived 11am - 50pkt - Sand arrived 12.30pm - 1load (10wheels) |
4) Feedback / problem: - Tom came 12pm, decide not to do box up first for water piping at the side. With that decision, Hassan only dismantle the scaffolding to allow digging job for the front drainage system. - The roof material should be arrived at the contractor factory by today, but when Jason called to check, their supervisor haven't getting notice about it. Jason check with Mr Tan, there will be a few day delayed. |
5) Work progress: - - - - |
2013/01/21 (Mon): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: pm - pm raining |
2) Daily issue / task: - Tony came, advise: i) Ground floor & 1st floor aircond must use at least 3HP ii) Have to install basic lighting to show buyer. |
3) Goods ordered / received: - Order cement - 50pkt - Order kapur - 50pkt - Order Sand - 1load |
4) Feedback / problem: - NIL |
5) Work progress: - - - - |
2013/01/19 (Sat): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: -NIL |
3) Goods ordered / received: - Dustbin arrived 2pm |
4) Feedback / problem: - NIL |
5) Work progress: - - - - |
2013/01/18 (Fri): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: - Aaron & Tom Yeap came 2.30pm to discuss about the schedule & preparation of installing windows & doors. |
3) Goods ordered / received: - Order dustbin |
4) Feedback / problem: - NIL |
5) Work progress: - Plaster - Plumbing - Digging for drainage (front) |
2013/01/17 (Thu): |
1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: 5pm raining |
2) Daily issue / task: - Hanif digging front area for drainage job, but encounter a concrete & old piping under, need to wait for hacking machine to continue. - |
3) Goods ordered / received: - Sand arrived 3.30pm - 1load (10 wheels) - Cement arrived 4.30pm - 50pkt |
4) Feedback / problem: - NIL |
5) Work progress: - Plaster |
2013/01/16 (Wed): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: - Tom came 1.30pm to meet with plumbing supervisor Keong, answer all his question. |
3) Goods ordered / received: - Kapur arrived 2.30pm - 100pkt - Cement arrived 3.30pm - 50pkt |
4) Feedback / problem: - Yesterday night heavy rain affected some plaster done outside. |
5) Work progress: - Plaster (outside) |
2013/01/15 (Tue): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: - CCTV job done today. - Steel structure first phase done today, wait for rooftop material. Estimated start 2nd phase next Monday. |
3) Goods ordered / received: - Red bricks arrived 5pm - 1pallet - Cement arrived 5pm - 25pkt - Order Kapur - 100pkt; Sand - 1load; Cement - 100pkt |
4) Feedback / problem: - NIL |
5) Work progress: - rooftop brick wall - Plaster - Steel structure |
2013/01/14 (Mon): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: - Jason borrow water pump from Alam to let Hanif pump out stagnant water, and clean the pool as well. |
3) Goods ordered / received: - Sand arrived 12.30pm - 1load (6 wheels) - Red bricks arrived 5pm - 1pallet - Cement arrived 5pm - 25pkt |
4) Feedback / problem: -NIL |
5) Work progress: - Plaster - Plumbing - Ceiling - Steel structure |
2013/01/12 (Sat): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to open up part of workers "hostel" for plumbing/wiring job, after the plaster job completed. |
1) Weather: No rain |
2) Daily issue / task: *** Aaron give RM700 petty cash to Jason - CIMB 000129 - CCTV & alarm works done. Dak said call him before put up ceiling to make sure all wiring levels are correct. - Aaron give RM100 to Ateh, as today salary/payment |
3) Goods ordered / received: - Sand arrived 3.40pm - 1load (6 wheels) - Order red bricks - 2 pallet - Order sand (deliver on Monday) - 1 load |
4) Feedback / problem: - Ateh came to work, but again need to borrow all kind of tools. Jason confirmed with Aaron, that Ateh need to figure it out himself. |
5) Work progress: - Steel structure - Drain |
2013/01/11 (Fri): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. |
1) Weather: 3pm - pm raining |
2) Daily issue / task: - Ateh (drain) came to work 11am. - Electrical & plumbing not working today. - |
3) Goods ordered / received: - Cement arrived 2pm - 50pkt - Order dustbin, arrived 2pm. Paid cash RM150 |
4) Feedback / problem: - Ateh (drain) came to work, but didn't bring tools, said cannot work without hacking machine, handbarrow etc... Jason confirmed with Aaron that he need to figure it out himself, that he should prepare his own tools. - |
5) Work progress: - Plaster (outside & 2nd floor toilet) |
2013/01/10 (Thu): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. |
1) Weather: No rain |
2) Daily issue / task: - Cleaning & digging front drain to build a concrete slab. |
3) Goods ordered / received: - Order Cement 100pkt & Kapur 100pkt - Sand arrived 11.30am - 1load (6-wheel) - Kapur arrived 4.30pm - 100pkt - Cement arrived 4.30pm - 50pkt - Order 1 load of sand to be delivered on Sat (12/1). |
4) Feedback / problem: - Ateh called on morning said will come to work but again, didn't showed up. - Tom Yeap said he won't have to come until we are ready to install doors & windows. For those not aligned sub-frame he ask just remove it. - The walcrete still not delivered, so plaster workers have to mixed manually cement with kapur, but the outcome is not so good, the plastered wall are looks "cracking" (see pic), need to scheme before painting. Mak ask Jason to tell the workers try to mix with less kapur. Jason has informed Amin & Hassan to look into it. |
5) Work progress: - Steel Structure (welding) - Plumbing |
2013/01/09 (Wed): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to clean up the front drainage. |
1) Weather: No rain |
2) Daily issue / task: - Put Abate to all stagnant water area. - Called Ah Choy (ceiling), to meet him tmr (10/1) to confirm starting ceiling work by next week. - Called Edmond, he confirmed they will continue the job till completing the roof. He also request for payment. |
3) Goods ordered / received: - Sand arrived 2.30pm - 1load (6-wheel) |
4) Feedback / problem: - NIL |
5) Work progress: - Plaster (stairs) - Steel structure (welding) - Plumbing |
2013/01/08 (Tue): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to clean up the front drainage. |
1) Weather: No rain |
2) Daily issue / task: - Crane arrived 10.45; leave 6pm (the crane ordered by steel contractor, we does not responsible for anything) - |
3) Goods ordered / received: - Sand arrived 11.30am - 1load (6-wheel) - Cement arrived 4pm - 50pkt |
4) Feedback / problem: - An accident happened when install steel beam @ master bedroom. The steel beam fell down (but still chained to the crane)caused by not properly welded. Fortunately no one is hurt and nothing is damaged. The steel worker put it back using bigger nuts and welding it properly. - Jason think only 3 person to install such big construction of steel frame is too dangerous, no proper safety equipment was used, solely depends on experience. |
5) Work progress: - Plaster (2nd floor) - Steel Structure (installation) |
2013/01/07 (Mon): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to clean up the front drainage. |
1) Weather: No rain |
2) Daily issue / task: - Steel & plumbing workers both not working today. - Dak (CCTV) came. Jason inform him about need to re-adjust the height of CCTV wiring at 1st floor, as instruct by Tom. - Jason ask Hanif to hack 2 small corner of balcony @ master bedroom, for steel installation job tomorrow. - Hassan a few workers to other site. - Jason request Mak to send back the water pump, and a hacking tools. But Mak couldn't promised when, as he is busy. |
3) Goods ordered / received: - Kapur arrived 12.30pm - 100pkt - Order sand - 2loads - Order cement - 50pkt |
4) Feedback / problem: - DBKL came, check nothing's wrong. But asking us to "sponsor" for their magazine. Aaron approved Jason to pay RM150, with receipt given. - Hassan finds out a few sub-frame need to be re-adjust. Jason has informed Tom Yeap, they will come on 10/1 (Thu) to work. - |
5) Work progress: - - - - |
2013/01/05 (Sat): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to clean up the front drainage. |
1) Weather: 2.15pm - 3pm raining |
2) Daily issue / task: - Jason give contact to Mr Tan (steel) to let them order the crane themselves. |
3) Goods ordered / received: - Sand arrived 11.30am - 1load (6-wheel) - Cement arrived 3.45pm - 50pkt |
4) Feedback / problem: - NIL |
5) Work progress: - - - - |
2013/01/04 (Fri): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) To build a concrete slab to widen the gate entrance. 3) Need to clean up the front drainage. |
1) Weather: 4.30pm - 6pm raining |
2) Daily issue / task: - 9am NLC came do mosquito fogging at site (RM200 paid cash) - 11am meeting with Aaron & Amin to discuss site operation issues. - Brain (landlord) came 3.30pm with a friend. Took some photos, no complaint. |
3) Goods ordered / received: - Order dustbin, arrived 1pm |
4) Feedback / problem: - Called Ateh (drain), still no answer. - Steel structure workers not coming today, got work at other site. |
5) Work progress: - (heavy rain too dark not taken pictures) - - - |
2013/01/03 (Thu): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am) 3) To build a concrete slab to widen the gate entrance. 4) Need to clean up the front drainage. |
1) Weather: No rain |
2) Daily issue / task: - Today 2nd floor start plastering. - Investor came visit site 11.45am, Aaron attend to them. - |
3) Goods ordered / received: - Cement arrived 11am - 50pkt - |
4) Feedback / problem: - Jason confirmed with plumbing supervisor (Keong) that they will use waterproof cement to cover piping holes. |
5) Work progress: - - - - |
2013/01/02 (Wed): |
Follow up: 1) To put an extra tube (2-3") from Guard House to the bungalow. 2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am) 3) To build a concrete slab to widen the gate entrance. 4) Need to clean up the front drainage. |
1) Weather: 4pm - 5.30pm raining |
2) Daily issue / task: - Mak took back the water pump - Steel structure supervisor said need us to help order crane on 8/1 (Tue) - Plumbing (Chiew) start working today. Marking all the hole and confirmed the plan with Tom on the spot. |
3) Goods ordered / received: - Order cement - 50pkt - Jason buy mesh wire - 5 rolls (RM8.50/roll) |
4) Feedback / problem: - Steel workers stop work at 4pm due to raining. - Ateh said need to arrange for his kid's first day school, cannot come to work. |
5) Work progress: - - - - |
2013/01/02 (Wed): |
Follow up: 1) 2) |
1) Weather: pm - pm raining |
2) Daily issue / task: - - |
3) Goods ordered / received: - - |
4) Feedback / problem: - - |
5) Work progress: - - - - |